By: Gary D. Quesada, Hon. Aff. AIA, J.D.
Cavanaugh & Quesada, PLC
On July 11, 2011, the Michigan Supreme Court decided the case of Miller-Davis v. Ahrens, __ Mich __ (2011), which held that Michigan’s special statute of repose, MCL 600.5839, does not apply to contract-based construction claims. This decision means that contractors are at greater risk for lawsuits.
In 1967, Michigan enacted MCL 600.5839, the special statute of repose for claims arising from improvements to real property. Section 5839 barred all claims for “injuries to persons or property” against architects, engineers and contractors that arose more than six years after “use, occupancy or acceptance” of the improve- ment.
Originally, the statute was understood to apply only to third-party claims, and Michigan courts so held. In 1988, Michigan enacted an amendment that was held by several courts to have expanded the statute of repose to include contractual claims as well as third-party claims. However, the Supreme Court never addressed this issue.
Miller-Davis involved a claim by a general contractor against a subcontractor for breach of contract. The issue was the construction of a natatorium roof, which the general contractor alleged was improperly constructed by the subcontractor. The subcontractor argued the claim was brought later than six years after first use, occupancy or acceptance of the improvement, and was therefore “reposed.” The Michigan Court of Appeals agreed and held the claim was barred. Plaintiff then sought review by the Michigan Supreme Court.
In the Supreme Court, the plaintiff argued the statute of repose did not apply to its claim, which was based on breach of contract and not an “injury to person or property.” The Supreme Court reversed the lower court and held that the statute of repose “does not apply to a breach of contract claim for a defect in a building improvement.” In making its ruling, the court cited with approval the federal case of Garden City Osteopathic Hosp v HBE Corp, 55 F3d 1126 (CA 6, 1995).
The Miller-Davis decision significantly extends the duration contractors can be sued for building defects. The impact of the case is likely to be that warranty claims by building owners for defective work will be brought long after the building has been occupied. Owners have contracts with their prime contractor, and often have direct contracts with specialty contractors. There is no longer any repose period for claims based on these contracts. By statute, warranty claims may be brought up to 6 years after a breach is discovered. Therefore, owners may bring suit up to 6 years after discovery of a latent defect, no matter when that discovery occurs.
The Garden City case cited by the Supreme Court is as example of the potential application of Miller-Davis. Garden City involved an owner’s claim brought against a contractor approximately 21 years after construction. Contractors should now be more careful to review their contracts and when possible, seek to limit their contractual obligations, including indemnification and warranty provisions, to reasonable durations.
For more information about the Miller-Davis decision and the Michigan statute of repose, you may contact Gary Quesada at Cavanaugh & Quesada, PLC, 1027 S. Washington Ave, Ste A, Royal Oak, MI 48067, Tel: (248) 543-8320.
No comments:
Post a Comment